Project statistics dialog displays summary information about a project.
If baseline copy of a schedule is saved then baseline values are displayed for comparison.
π· On the main menu click project, select project information
π· The project information dialog box appears
π·Click on project statistics
π·You will get start, finish, duration, work, cost values for current, baseline, actual, remaining
π·Also, you will get percent complete duration %, work %
If baseline copy of a schedule is saved then baseline values are displayed for comparison.