Monday, February 22, 2021

Tracking Progress

Project statistics dialog displays summary information about a project.
If baseline copy of a schedule is saved then baseline values are displayed for comparison.
πŸ‘· On the main menu click project, select project information
πŸ‘· The project information dialog box appears
πŸ‘·Click on project statistics
πŸ‘·You will get start, finish, duration, work, cost values for current, baseline, actual, remaining
πŸ‘·Also, you will get percent complete duration %, work %

Monday, February 15, 2021

Saving Baseline

The baseline information is a snapshot of project plan information at a particular point of time. To save baseline follow these steps
πŸ‘· Click tools, tracking, save baseline
πŸ‘· The save baseline dialog appears
πŸ‘· Make sure save baseline option is selected
πŸ‘· In the box under the save baseline option make  sure that baseline is selected
πŸ‘· Under 'For:' make sure the 'Entire Project' is selected
πŸ‘· Click 'OK'

Saturday, February 13, 2021

Assigning Resources

By creating an assignment you specify both the resources assigned to a task and their associated assignment units 1.
πŸ‘·In the assign resources dialog Task - Resources List options - Resources from project 1
To assign resources from project server
πŸ‘·Select the task to which you want to assign a resource
πŸ‘·Click assign resource
πŸ‘·The assign resource dialog appears, expand resource list option.
πŸ‘·Under add resource option select from project server
πŸ‘·The Build Team for Project 1 dialog appears
πŸ‘·Select the resources you want and click Add
πŸ‘·Now repeat the steps that appear in highlighted color
 


Wednesday, February 10, 2021

Task Dependencies

Link various tasks that are dependent on each other.
The project plan will look like a real schedule.
There are 04 (four) types of dependencies
πŸ‘· Finish-to-start
πŸ‘· Finish-to-finish
πŸ‘· Start-to-start
πŸ‘· Start-to-finish
Creating finish to start dependency
πŸ‘· Select the task you want to link
πŸ‘· On the standard tool bar click link task πŸ”— else use (ctrl+f2)
To apply any tak dependencies follow these steps
πŸ‘· Select the task that is to become the successor
πŸ‘· On the standard tool bar click task information or double click the task to open the task information dialog box
πŸ‘· Click predecessors tab
πŸ‘· Click the blank row in the task name field and then click the down arrow key to see the list of tasks
πŸ‘· Click the task that is to be the predecessor to the current task
πŸ‘· Click the type field then select the type of dependency
πŸ‘· Click ok
The project guide also provides a quick way to create most common links
πŸ‘· Choose the task on the project guide
πŸ‘· Select the Schedule task
πŸ‘· Select the task you want to link and then choose the link

Defining Milestones

A milestone represents a significant landmark, decision point or turning point in the life of a project.
They Can be considered as reporting points. 
The milestone marker and date are drawn in the chart area of Gantt Chart
πŸ‘· To create a milestone
        ~ Enter the number 0 in the duration field
πŸ‘· To change a regular task into a milestone do the following
        ~ Select the task you want to make milestone
        ~ On the standard tool bar click task information and then click the advanced tab
        ~ Select the mark task as milestone check box

Tuesday, February 9, 2021

Organizing Task Into Outline

Outlining organizes tasks into structure representing hierarchy of task
Collapsing a outline suppresses the display of a sub task
Task at higher outline is called summary task and at lower outline is called sub task
πŸ‘· Creating a subtask
        --Select the task(s)
        --On formatting toolbar click indent πŸ‘‰ (else use Alt+Shift+Right Arrow Key)
πŸ‘· Creating a summary task
        --Select the task(s)
        --On formatting toolbar click outdent πŸ‘‰ (else use Alt+Shift+Left Arrow Key)


Entering Tasks and Duration

To enter tasks in your pproject plan follow these steps
πŸ‘· Make sure you are working in Gantt Chart View (click view Gantt Chart)
πŸ‘· Type the name of task in the task field
πŸ‘· Press enter or down key to move to the next row (as soon as you press enter project supplies default duration 1 day? and it also supplies a default start and finish date)
πŸ‘·Enter the required duration of task in the duration field and the start date in the start field (project automatically calculates the finish date for you)

How to Start Project Professional

 πŸ‘· On your computer or laptop keyboard press the following keys
 πŸ‘· Start-Run-Type winproj
 πŸ‘· Window-R & Type winproj yhen press enter

Project Web Access - How to get the home page

Project Web Access - How to get the home page πŸ‘· Open the internet browser πŸ‘· Type the URL given to you by your administrator πŸ‘· Enter your ...