Saturday, April 10, 2021

Project Web Access - How to get the home page

Project Web Access - How to get the home page

πŸ‘· Open the internet browser

πŸ‘· Type the URL given to you by your administrator

πŸ‘· Enter your user name and password

πŸ‘· Click ok



Saturday, February 13, 2021

Assigning Resources

By creating an assignment you specify both the resources assigned to a task and their associated assignment units 1.
πŸ‘·In the assign resources dialog Task - Resources List options - Resources from project 1
To assign resources from project server
πŸ‘·Select the task to which you want to assign a resource
πŸ‘·Click assign resource
πŸ‘·The assign resource dialog appears, expand resource list option.
πŸ‘·Under add resource option select from project server
πŸ‘·The Build Team for Project 1 dialog appears
πŸ‘·Select the resources you want and click Add
πŸ‘·Now repeat the steps that appear in highlighted color
 


Wednesday, February 10, 2021

Task Dependencies

Link various tasks that are dependent on each other.
The project plan will look like a real schedule.
There are 04 (four) types of dependencies
πŸ‘· Finish-to-start
πŸ‘· Finish-to-finish
πŸ‘· Start-to-start
πŸ‘· Start-to-finish
Creating finish to start dependency
πŸ‘· Select the task you want to link
πŸ‘· On the standard tool bar click link task πŸ”— else use (ctrl+f2)
To apply any tak dependencies follow these steps
πŸ‘· Select the task that is to become the successor
πŸ‘· On the standard tool bar click task information or double click the task to open the task information dialog box
πŸ‘· Click predecessors tab
πŸ‘· Click the blank row in the task name field and then click the down arrow key to see the list of tasks
πŸ‘· Click the task that is to be the predecessor to the current task
πŸ‘· Click the type field then select the type of dependency
πŸ‘· Click ok
The project guide also provides a quick way to create most common links
πŸ‘· Choose the task on the project guide
πŸ‘· Select the Schedule task
πŸ‘· Select the task you want to link and then choose the link

Defining Milestones

A milestone represents a significant landmark, decision point or turning point in the life of a project.
They Can be considered as reporting points. 
The milestone marker and date are drawn in the chart area of Gantt Chart
πŸ‘· To create a milestone
        ~ Enter the number 0 in the duration field
πŸ‘· To change a regular task into a milestone do the following
        ~ Select the task you want to make milestone
        ~ On the standard tool bar click task information and then click the advanced tab
        ~ Select the mark task as milestone check box